Charging Expenses to a Sponsor: Allowable and Unallowable Costs
One primary responsibility of a Principal Investigator (PI) or Project Director (PI) on a sponsored project is to ensure that all costs charged to a sponsored project meet the definitions of allowable, allocable and reasonable. This determination is based on both federal rules and on the specific guidelines of the sponsoring agency and must conform to any related guidelines and policies specific to St. John Fisher University. The process is guided and overseen by the Office of Sponsored Programs and Foundation Relations and the Business Office.
Important Definitions
A cost must be necessary to carry out the project AND must follow all applicable policies and guidelines. It must also be adequately documented, be accorded consistent treatment across like circumstances, and be deemed reasonable and allocable to the specific project. For further information, see 2 CFR 200.403.
Reasonable
The nature and the amount of the cost does not exceed what would be incurred by a prudent person under similar circumstances. For further information, see 2 CFR 200.404.
Allocable
The cost must have a demonstrable and specific benefit to the sponsored project. For further information, see 2 CFR 200.405.
Consistent
The cost must be treated in the same manner (i.e., charged as either a direct or indirect cost) when used in like circumstances. This applies to any work done at the University, regardless of the funding source.
Direct Costs
Expenses that can be identified specifically with a sponsored project or can be assigned to that sponsored project with a high degree of accuracy.
Indirect Costs (also referred to as Facilities and Administrative or F&A costs)
Costs incurred for common or joint objectives that cannot be identified readily or specifically with a particular sponsored project or any other institutional activity.
F&A costs may allowable as direct costs if specific conditions are met. These conditions include:
- The item or service is absolutely required to carry out the project;
- The cost can be specifically identified; and
- The costs and appropriately justified for the project.
Quotes
Auditable documentation; required for purchases under certain conditions:
- For purchases up to $3,000, no quotes are required.
- For purchases above $3,000, every effort should be made to obtain at least two competitive quotes.
Select Allowable and Unallowable Expenses
In general, an expense for a non-federal grant is allowable if the following two conditions are met:
- It is consistent with the terms of the non-federal award, AND
- It would be allowable with Fisher funds.
2 CFR 200.400 details the types of costs that cannot be charged to federal awards, either as direct or indirect costs. A few examples of these costs are alcoholic beverages, certain types of advertising, entertainment/amusement, bad debts, contributions and donations, fines, and penalties.
The chart below is intended as a quick reference for common types of costs. This section is not exhaustive, and the Business Office should be contacted for specific questions concerning a cost, preferably in advance of the incurrence of a cost.
Budget Item | Type: Allowable or Unallowable Expense |
---|---|
Alcoholic Beverages | Unallowable |
Capital Equipment (items costing more than $3,000 and having a useful life of more than one year) |
Depends: In general, to purchase capital equipment with sponsored funds, a line item for the equipment must be in the categorical budget as awarded by the sponsor; otherwise, Fisher must seek specific approval from the funding agency. Allowable: Shipping charges, upgrades, regular upkeep, and costs incurred to make an item of capital equipment useable (see §200.452). If Fisher is instructed by the federal awarding agency to dispose of the equipment, that cost is allowable as well (see §200.439). Unallowable: Warranty costs or training. |
Conference Fees (including meals, transportation, and lodging) |
Allowable: The purpose of the conference or of participation at the conference must be “the dissemination of technical information” related to the project (this can include informal discussion of “work in progress”). For all conference travel, the traveler must provide justification details within the approved budget. |
Computer/Computing Devices |
Depends: May be considered as a supply if under $5,000. May be allowable if the computers are essential for the performance of the specific project and their use is beyond the normal use and application of computers in the day-to-day operations of the University. Their use must be directly related and specifically identifiable to the project. |
Entertainment | Unallowable: This includes meals that are not eligible for reimbursement (see Food). |
Food (including catering, meals and snacks) | Unallowable: In general, federal funds may not be used to purchase food. |
Maintenance | Unallowable as a direct cost |
Memberships: Civic, Community and Social Organizations |
Unallowable |
Memberships: Institutional Memberships | Unallowable as a direct cost |
Memberships: Professional Organizations |
Depends: Membership in professional organizations may be allowable if the expense meets both of the following criteria:
In some circumstances, membership may be allowable if the PI/PD can document that the PI needs to be a member of the professional organization in order to conduct the project AND the PI would not otherwise be a member. |
Office Supplies |
Allowable: Supplies purchased for technical or scientific use on a project may be an allowable expense if appropriately justified; they must be consumed during the life of the project. Unallowable: General purpose office supplies, which are already built into the F&A rate. |
Postage/Shipping Costs | Unallowable as a direct cost: May be allowable if PI/PD can document that the expense can be allocated to a specific award and is justified as being a direct cost of the project, rather than part of Fisher’s indirect costs. |
Professional Services |
Allowable: Approved contracts for individual professional services who are not employees of Fisher Unallowable: Professional and consulting services rendered by Fisher employees |
Subscriptions | Unallowable as a direct cost: If the PI/PD can document that 1) access to the journal is required in order to carry out the project; 2) Fisher does not already provide the journal; AND 3) the PI/PD would not otherwise subscribe, it may be allowable. |
Supplies | Allowable: Materials, supplies, and parts necessary to carry out the project. Shipping costs for supplies are a proper part of supplies costs. |
Telephone | Depends: Local telephone costs are unallowable as a direct cost on federal awards. In some circumstances, long-distance telephone costs may be allowable it is specified in the grant guidelines and the PI can: a) document that the expense can be allocated to a specific award and b) is justified as being a direct cost of the project, rather than part of Fisher’s indirect costs. |
Travel |
Allowable: The purpose of the trip must be related to the performance of the project, and either domestic or foreign travel respectively must have been included as a line item in the categorical budget as awarded by the sponsor or in an approved revised budget as approved. For all travel using sponsored funds, the traveler must provide justification details. Reimbursement for travel expenses using federal funds follows the same policies as reimbursement with Fisher funds for similar purposes—i.e., travelers must choose the least expensive method of travel or provide justification for using a more expensive method. Lodging Federal per diem rates may be used to develop budget during the pre-award stage, but itemized receipts for actual expenses are required. Meals & Incidentals Federal per diem rates may be used to develop budget during the pre-award stage, but itemized receipts for actual expenses are required. Federal funds cannot be used for alcoholic beverages even if part of a meal. Mileage has the most current rates. Please note the following additional requirements for travel using federal funds: Airfare Choose the least expensive coach class flight on a U.S. carrier. Foreign travel Many federal funding agencies require prior approval for or may not allow foreign travel. If foreign travel is not specified in the awarded budget, check with the Business Office. |
Administrative and clerical salaries included in the F&A rate |
Unallowable: Administrative salaries that are built into the indirect cost (F&A) rate may not be included in the grant budget. |